[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909559":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909559,587,1,"单选题","项目评价中，保证项目财务可持续的必要条件是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","各年的筹资现金流量满足投资活动要求",false,{"key":16,"text":17,"correct":14},"B","拥有比较大的财务效益",{"key":19,"text":20,"correct":14},"C","合理安排还本付息期",{"key":22,"text":23,"correct":24},"D","各年累计盈余资金不出现负值",true,"2020版教材P293 财务生存能力分析，应在财务分析辅助表和利润与利润分配表的基础上编制财务计划现金流量表，通过考察项目计算期内的投资、融资和经营活动所产生的各项现金流入和流出，计算净现金流量和累计盈余资金，分析项目是否有足够的净现金流量维持正常运营，以实现财务可持续性。财务可持续性应首先体现在有足够大的经营活动净现金流量，其次，各年累计盈余资金不应出现负值。若出现负值，应进行短期借款，同时分析该短期借款的年份长短和数额大小，进一步判断项目的财务生存能力。短期借款应体现在财务计划现金流量表中，其利息应计入财务费用。为维持项目正常运营，还应分析短期借款的可靠性。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]