[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909549":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909549,587,1,"单选题","工程项目管理的中心任务是进行工程项目（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","目标控制",true,{"key":16,"text":17,"correct":18},"B","质量控制",false,{"key":20,"text":21,"correct":18},"C","进度控制",{"key":23,"text":24,"correct":18},"D","安全控制","2020版教材P286 工程项目管理工作的中心任务是进行工程项目目标控制，因此，工程项目策划是工程项目管理的前提，也是工程造价管理的前提。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]