[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909547":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909547,587,1,"单选题","在中国境外投资的建设项目财务基准收益率的测定，应首先考虑（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","国家在一定时期的发展战略",false,{"key":16,"text":17,"correct":14},"B","市场需求、资金时间价值、项目目标",{"key":19,"text":20,"correct":21},"C","国家风险因素",true,{"key":23,"text":24,"correct":14},"D","政府资源、宏观调控意图、履行政府职能等因素","2020版教材P292 详见在中国境外投资的建设项目财务基准收益率的测定，应首先考虑国家风险因素。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]