[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909544":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909544,587,1,"单选题","限额设计的实施是建设工程造价目标的动态反馈和管理过程，其目标管理的总结阶段是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","目标制定",false,{"key":16,"text":17,"correct":14},"B","目标分解",{"key":19,"text":20,"correct":14},"C","目标推进",{"key":22,"text":23,"correct":24},"D","成果评价",true,"2020版教材P306 本题考查的是限额设计。限额设计的实施是建设工程造价目标的动态反馈和管理过程，可分为目标制定、目标分解、目标推进和成果评价四个阶段。成果评价是目标管理的总结阶段。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]