[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909539,587,1,"单选题","工程项目投资方案现金流量表不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投资现金流量表",false,{"key":16,"text":17,"correct":14},"B","资本金现金流量表",{"key":19,"text":20,"correct":21},"C","项目投资经济费用效益流量表",true,{"key":23,"text":24,"correct":14},"D","投资各方现金流量表","2020版教材P296 本题考查的是工程项目经济评价报表的编制。投资方案现金流量表由现金流入、现金流出和净现金流量构成，其具体内容随投资方案经济效果评价的角度、范围和方法不同而不同，其中，主要有投资现金流量表、资本金现金流量表、投资各方现金流量表和财务计划现金流量表。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]