[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909445":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909445,587,1,"单选题","在项目总投资和投资风险一定的条件下，项目资本金比例越高，则（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","权益投资人投入项目的资金越多，承担的风险越高",true,{"key":16,"text":17,"correct":18},"B","权益投资人投入项目的资金越多，承担的风险越低",false,{"key":20,"text":21,"correct":18},"C","权益投资人投入项目的资金越低，提供债务资金的债权人承担的风险越低",{"key":23,"text":24,"correct":18},"D","权益投资人投入项目的资金多少与提供债务资金的债权人承担的风险无关","2020版教材P242 在项目总投资和投资风险一定的条件下，项目资本金比例越高，权益投资人投入项目的资金越多，承担的风险越高，而提供债务资金的债权人承担的风险越低。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]