[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909380":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909380,587,1,"单选题","工程寿命周期成本分析法的局限性之一是假定工程对象有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","固定的运行效率",false,{"key":16,"text":17,"correct":14},"B","确定的投资额",{"key":19,"text":20,"correct":21},"C","确定的寿命周期",true,{"key":23,"text":24,"correct":14},"D","固定的功能水平","2020版教材P225 尽管寿命周期成本分析方法得到越来越广泛的应用，但仍存在着局限性：①假定项目方案有确定的寿命周期；②在项目早期进行评价的准确性难以保证；③工程寿命周期成本分析的高成本未必适用于所有项目。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]