[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909343":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909343,587,1,"单选题","应用价值工程进行功能评价时，效果评价对象的价值指数V1＜1，则正确的价值是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","降低评价对象的现实成本",true,{"key":16,"text":17,"correct":18},"B","提出评价对象的过剩功能",false,{"key":20,"text":21,"correct":18},"C","降低评价对象的功能水平",{"key":23,"text":24,"correct":18},"D","不将评价对象作为改进对象","2020版教材P216 V1＜1。评价对象的成本比重大于其功能比重，表明相对于系统内的其他对象而言，目前所占的成本偏高，从而会导致该对象的功能过剩。应将评价对象列为改进对象，改善方向主要是降低成本。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]