[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909335":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909335,587,1,"单选题","关于财务内部收益率的说法，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","财务内部收益率大于基准收益率时，技术方案在经济上可以接受",true,{"key":16,"text":17,"correct":18},"B","财务内部收益率是一个事先确定的基准折现率",false,{"key":20,"text":21,"correct":18},"C","财务内部收益率受项目外部参数的影响较大",{"key":23,"text":24,"correct":18},"D","独立方案用财务内部收益率评价与财务净现值评价，结论通常不一致","选项A正确，财务内部收益率大于基准收益率时，技术方案在经济上可以接受。选项B错误，内部收益率指标考虑了资金的时间价值以及项目在整个计算期内的经济状况；能够直接衡量项目未回收投资的收益率；不需要事先确定一个基准收益率，而只需要知道基准收益率的大致范围即可。选项C错误，内部收益率大小不受外部参数影响，完全取决于投资过程的现金流量。选项D错误，用财务内部收益率与财务净现值均可对独立方案进行评价，且结论是一致的。2020教材P176-185",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]