[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909318":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909318,587,1,"单选题","（ ）时，投资额大的方案可行，投资的增量完全可以由经营成本的节约来得到补偿。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","增量投资收益率小于基准投资收益率",false,{"key":16,"text":17,"correct":14},"B","增量投资收益率等于基准投资收益率",{"key":19,"text":20,"correct":14},"C","增量投资收益率小于或等于基准投资收益率时",{"key":22,"text":23,"correct":24},"D","增量投资收益率大于基准投资收益率时",true,"2020版教材P188 本题考查的是经济效果评价方法。当得到的增量投资收益率大于基准投资收益率时，则投资额大的方案可行，投资的增量完全可以由经营成本的节约来得到补偿。反之，投资额小的方案为优选方案。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]