[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909305":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909305,587,1,"单选题","在评价投资方案经济效果时，如果 A、B两个方案中缺少任何一个，另一个就不能正常运行，则 A、B两方案称为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组合型",false,{"key":16,"text":17,"correct":18},"B","互补型",true,{"key":20,"text":21,"correct":14},"C","混合型",{"key":23,"text":24,"correct":14},"D","相关型","2020版教材P186 互补型方案是指在方案之间存在技术经济互补关系的一组方案。根据互补方案之间相互依存的关系，互补方案可能是对称的，如建设一个大型电站时，必须同时建设铁路、电厂，它们无论在建成时间、建设规模上都要彼此适应，缺少其中任何一个项目，其他项目就不能正常运行，它们之间是互补的，又是对称的。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]