[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909272":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909272,587,1,"单选题","某建设项目以财务净现值为指标进行敏感性分析的有关数据见下表，则该建设项目投资额变化幅度的临界点是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","+8.13%",false,{"key":16,"text":17,"correct":14},"B","+10.54%",{"key":19,"text":20,"correct":21},"C","+12.31%",true,{"key":23,"text":24,"correct":14},"D","+16.37%","2020版教材P200 所谓临界点指的是净现值为0时，对应的投资幅度。从表格我们可以看出：幅度变化在+20%，净现值为-100.幅度变化在+10%，净现值为30.所以：i=10%+（20%-10%)*(30\u002F(30+I-100I))=12.31%",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]