[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909233":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909233,587,1,"单选题","根据《标准施工招标文件》，除专用合同条款另有约定外，解释合同文件包括：①技术标准和要求；②图纸；③中标通知书；④投标函及投标函附录；⑤合同协议书。以上解释合同文件的优先顺序为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","⑤—①—②—④—③",false,{"key":16,"text":17,"correct":18},"B","⑤—③—④—①—②",true,{"key":20,"text":21,"correct":14},"C","③—④—⑤—②—①",{"key":23,"text":24,"correct":14},"D","⑤—②—③—①—④","2020教材P144-148 组成合同的各项文件应互相解释、互为说明。除专用合同条款另有约定外，解释合同文件的优先顺序如下：①合同协议书；②中标通知书；③投标函及投标函附录；④专用合同条款；⑤通用合同条款；⑥技术标准和要求；⑦图纸；⑧已标价工程量清单i⑨其他合同文件。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]