[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909230":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909230,587,1,"单选题","某工程的双代号网络计划如下图所示(单位：天)，该网络计划的关键线路为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→③→⑤→⑥",false,{"key":16,"text":17,"correct":18},"B","①→③→④→⑤→⑥",true,{"key":20,"text":21,"correct":14},"C","①→②→③→④→⑤→⑥",{"key":23,"text":24,"correct":14},"D","①→②→③→⑤→⑥","本题考查的是网络计划时间参数的计算。选项A：17天；选项B：18天；选项C：17天；选项D：16天。选项B线路最长，是关键线路，故B选项正确。2020教材P123-132",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]