[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909225":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909225,587,1,"单选题","A工作后有紧后工作 B、 C，它们的持续时间分别为5天、4天和6天； B、C工作最迟完成时间分别为25天和23天，则A工作的最迟开始时间为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","8",{"key":19,"text":20,"correct":21},"C","12",true,{"key":23,"text":24,"correct":14},"D","16","2020教材P123-132",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]