[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909223":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909223,587,1,"单选题","某工程双代号网络计划如下图所示，其中关键线路有（ ）条。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":14},"C","3",{"key":22,"text":23,"correct":24},"D","4",true,"2020版教材P118 关键线路：线路上所有工作的持续时间总和称为该线路的总持续时间。总持续时间最长的线路称为关键线路。故关键线路有：①⑤⑦，①②④⑤⑦，①③⑥⑦，①②④⑥⑦。4条",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]