[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909220":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909220,587,1,"单选题","在不影响其紧后工作最早开始时间的前提下，本工作可利用的机动时间为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差",false,{"key":16,"text":17,"correct":18},"B","自由时差",true,{"key":20,"text":21,"correct":14},"C","最迟开始时间",{"key":23,"text":24,"correct":14},"D","最迟完成时间","2020版教材P123 本题考查的是网络计划时间参数的计算。工作的自由时差是指在不影响其紧后工作最早开始时间的前提下，本工作可利用的机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]