[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909217":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909217,587,1,"单选题","某工程双代号时标网络计划如下图所示，根据第6周末实际进度检查结果绘制的前锋线，下列描述正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","C工作实际进度拖后2周，影响工期2周",false,{"key":16,"text":17,"correct":14},"B","D工作实际进度超前2周，不影响工期",{"key":19,"text":20,"correct":14},"C","E工作实际进度拖后1周，不影响工期",{"key":22,"text":23,"correct":24},"D","E工作实际进度拖后1周，影响总工期1周",true,"2020版教材P137 本题考查的是前锋线比较法。选项A，C工作实际进度拖后2周，其总时差为1周，所以影响工期1周；选项B，D工作实际进度拖后3周，其总时差为1周，所以影响总工期2周；选项C，E工作实际进度拖后1周，影响总工期1周。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]