[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909216":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909216,587,1,"单选题","某工程双代号时标网络计划如下图所示，其中工作E的自由时差为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0周",false,{"key":16,"text":17,"correct":14},"B","1周",{"key":19,"text":20,"correct":21},"C","2周",true,{"key":23,"text":24,"correct":14},"D","3周","2020版教材P134 本题考查的是双代号时标网络计划。①以终点节点为完成节点的工作，其自由时差与总时差必然相等。②其他工作的自由时差就是该工作箭线中波形线的水平投影长度。但当工作之后只紧接虚工作时，则该工作箭线上一定不存在波形线，而其紧接的虚箭线中波形线水平投影长度的最短者为该工作的自由时差。E工作紧接的虚箭线中波形线水平投影长度最短为2周，即工作E的自由时差为2周。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]