[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909208":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909208,587,1,"单选题","A工作后有紧后工作 B、 C，它们的持续时间分别为5d、4d和6d； B、C工作最迟完成时间分别为25d和23d，则A工作的最迟开始时间为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4d",false,{"key":16,"text":17,"correct":14},"B","8d",{"key":19,"text":20,"correct":21},"C","12d",true,{"key":23,"text":24,"correct":14},"D","16d","2020版教材P125 本题考查的是网络计划时间参数的计算。已知LFB=25，则LSB=LFB-DB=25-4=21;已知LFc=23，则LSc=LFc-Dc=23-6=17；则LFA=min{21，17}=17，故LSA=17-5=12。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]