[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909206":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909206,587,1,"单选题","某工程网络计划中，工作D有两项紧后工作，最早开始时间分别为17和20，工作D的最早开始时间为12，持续时间为3，则工作D的自由时差为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","3",{"key":22,"text":23,"correct":24},"D","2",true,"2020版教材P125 （5）计算工作的自由时差。工作自由时差的计算应按以下两种情况分别考虑：1）对于有紧后工作的工作，其自由时差等于本工作之紧后工作最早开始时间减本工作最早完成时间所得之差的最小值，即:min（17，20）-（12+3）=2。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]