[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909202,587,1,"单选题","某工程双代号网络计划中，工作N两端节点的最早时间和最迟时间如下图所示，则工作N总时差为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",true,{"key":16,"text":17,"correct":18},"B","1",false,{"key":20,"text":21,"correct":18},"C","2",{"key":23,"text":24,"correct":18},"D","3","2020版教材P127 本题考查的是网络计划时间参数的计算。TFN=min{\u002FT③}-ET②-DN=9-2-3=4。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]