[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909201,587,1,"单选题","（ ）是指在双代号网络计划中，以该节点为开始节点的各项工作的最早开始时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","节点最早时间",true,{"key":16,"text":17,"correct":18},"B","节点开始时间",false,{"key":20,"text":21,"correct":18},"C","最早开始时间",{"key":23,"text":24,"correct":18},"D","节点最迟时间","2020版教材P124 （1）节点最早时间。节点最早时间是指在双代号网络计划中，以该节点为开女台节点的各项工作的最早开始时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]