[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909199,587,1,"单选题","某工程双代号网络计划如下图所示，其中关键线路有（ ）条。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":18},"B","3",true,{"key":20,"text":21,"correct":14},"C","4",{"key":23,"text":24,"correct":14},"D","5","2020版教材P126 本题考查的是网络计划时间参数的计算。关键线路有三条，分别为：①—④—⑥—⑧；①—②—⑦—⑧；①—②—③—⑤—⑥—⑧。工期为20天。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]