[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909198":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909198,587,1,"单选题","某工程双代号时标网络计划如下图所示（单位：周），则在不影响总工期的前提下，工作E可以利用的机动时间为（ ）周。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","2020版教材P133 本题计算的是E工作的总时差，从图中可知，E的紧后工作HGI的总时差分别为0，4，2，则TFE=min(2+0，0+4，1+2)=2（周）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]