[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909197":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909197,587,1,"单选题","在工程网络计划中，关键线路是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单代号网络计划中总的工作持续时间最长的线路",true,{"key":16,"text":17,"correct":18},"B","双代号网络计划中由关键节点组成的线路",false,{"key":20,"text":21,"correct":18},"C","单代号搭接网络计划中总的工作持续时间最长的线路",{"key":23,"text":24,"correct":18},"D","双代号时标网络计划中无虚箭线的线路","2020版教材P118 单代号网络计划、双代号网络计划中总的持续时间最长的线路就是关键线路。但对于单代号搭接网络计划来说就不成立，因为搭接网络计划存在复杂的搭接关系，总的工作持续时间最长，但由于搭接关系的存在，不一定是关键线路；P132双代号时标网络自始至终没有波形线的线路是关键线路；P128双代号网络计划中由关键节点组成的线路并不一定是关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]