[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909196":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909196,587,1,"单选题","已知A工作的紧后工作为 B、C （B、C的紧前工作只有 A），持续时间分别为8天、7天、4天。A工作的最早开始时间为第9天。 B、C工作的最迟完成时间分别为第37天、39天，则A工作的自由时差应为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","O",true,{"key":16,"text":17,"correct":18},"B","1",false,{"key":20,"text":21,"correct":18},"C","13",{"key":23,"text":24,"correct":18},"D","18","2020版教材P127 FFA=min（ESB，ESC）-EFA，由于B、C的紧前工作为A，则B、C的最早开始时间就是A工作的最早完工时间。所以A工作的自由时差为0。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]