[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909195":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909195,587,1,"单选题","已知 A、B工作的紧后工作为 C、 D，其持续时间分别为3天、4天、2天、5天。 A、B工作的最早开始时间为第6天、4天，则D工作的最早完成时间为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","11",{"key":19,"text":20,"correct":14},"C","13",{"key":22,"text":23,"correct":24},"D","14",true,"2020版教材P127 EFD=ESD+5=max（6+3，4+4）+5=14（天）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]