[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909193,587,1,"单选题","关于网络图绘制规则，说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","双代号网络图中的虚箭线严禁交叉，否则容易引起混乱",true,{"key":16,"text":17,"correct":18},"B","双代号网络图中严禁出现循环回路，否则容易造成逻辑关系混乱",false,{"key":20,"text":21,"correct":18},"C","双代号时标网络计划中的虚工作可用波形线表示自由时差",{"key":23,"text":24,"correct":18},"D","单代号搭接网络图中相邻两工作的搭接关系可表示在箭线上方","2020版教材P119 应尽量避免网络图中工作箭线的交叉。当交叉不可避免时，可以采用过桥法或指向法处理",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]