[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909192":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909192,587,1,"单选题","已知甲、乙工作结束后丙工作开始，三项工作的持续时间分别为5天、7天、9天，甲、乙工作最早开始时间分别为第12天、11天，丙工作最迟完成时间为第29天，则甲工作的自由时差应为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","O",false,{"key":16,"text":17,"correct":18},"B","1",true,{"key":20,"text":21,"correct":14},"C","2",{"key":23,"text":24,"correct":14},"D","3","2020版教材P127 甲的紧后工作为丙，则FF甲=ES丙-EF甲=max（12+5，11+7）-（12+5）=1（天）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]