[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909191,587,1,"单选题","某工程双代号时标网络计划如下图所示，其中工作A的总时差为（ ）周。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","2",false,{"key":20,"text":21,"correct":18},"C","3",{"key":23,"text":24,"correct":18},"D","4","2020版教材P133 A工作的紧后工作D、E、G的总时差分别为2、O、1周，A工作的总时差=min(0+2,1+0,1+1)=1（周）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]