[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909189":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909189,587,1,"单选题","已知 A、B工作的紧后工作为 C，持续时间分别为11天、15天、19天， A、B工作最早开始时间分别为第18天、14天，C工作的最迟完成时间为第49天，则A工作的最迟开始时间应为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","19",true,{"key":16,"text":17,"correct":18},"B","21",false,{"key":20,"text":21,"correct":18},"C","18",{"key":23,"text":24,"correct":18},"D","30","2020版教材P127 LSA=LFA-II=LSC-11=49-19-11=19（天）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]