[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909185":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909185,587,1,"单选题","关于关键路线，下列说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在双代号时标网络中，从起始节点到终止节点，自始至终不出现波形线的是关键路线",false,{"key":16,"text":17,"correct":14},"B","在双代号网络图中，关键路线是工作持续时间最长的路线",{"key":19,"text":20,"correct":21},"C","关键路线上如果总时差为零，自由时差可以不为零",true,{"key":23,"text":24,"correct":14},"D","在单代号网络图中，从起始节点到终止节点，所有工作之间的时间间隔为零的线路为关键线路","2020版教材P126 本题考查的是网络计划时间参数的计算。工作的自由时差是其总时差的构成部分，所以，当工作的总时差为零时，其自由时差必然为零，可以不必进行专门计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]