[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909184":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909184,587,1,"单选题","某工程的双代号网络计划如下图所示（单位：天），该网络计划的关键线路为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①—③—⑤—⑥",false,{"key":16,"text":17,"correct":18},"B","①—③—④—⑤—⑥",true,{"key":20,"text":21,"correct":14},"C","①—②—③—④—⑤—⑥",{"key":23,"text":24,"correct":14},"D","①—②—③—⑤—⑥","2020版教材P118 (2）关键线路和关键工作。在关键线路法（CPM）中，线路上所有工作的持续时间总和称为该线路的总持续时间。总持续时间最长的线路称为关键线路，选项A的工期为17天；选项B的工期为18天；选项C的工期为17天；选项D的工期为16天。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]