[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909182":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909182,587,1,"单选题","某工程组织成倍节拍流水施工，4个施工段，4个施工过程的流水节拍分别为5，10，10，15，则该工程的流水工期为（）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50",false,{"key":16,"text":17,"correct":18},"B","55",true,{"key":20,"text":21,"correct":14},"C","60",{"key":23,"text":24,"correct":14},"D","70","首先计算流水步距为流水节拍的最大公约数为5，然后计算各施工过程所需的施工队数为1，2，2，3，最后计算流水工期=[4+(1+2+2+3)-1]×5=55(天)。2020教材P111-116",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]