[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909176":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909176,587,1,"单选题","某工程划分为3个施工过程、4个施工段，组织加快的成倍节拍流水施工，流水节拍分别为4天、4天和2天，则应派（ ）个专业工作队参与施工。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":14},"C","4",{"key":22,"text":23,"correct":24},"D","5",true,"本题考查的是流水施工的基本组织方式。本题采用的是加快成本节拍流水施工，首选确定流水步距，K=min[4，4，2]=2。再确定专业工作队数目，b1=4／2=2，b2=4／2=2，b1=2／2=1。于是参与工程流水施工的专业队总数n′=2+2+1=5(个)。2020教材P111-116",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]