[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909173":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909173,587,1,"单选题","下列对于固定节拍流水施工描述错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","所有施工过程在各个施工段上的流水节拍均相等",false,{"key":16,"text":17,"correct":18},"B","相邻施工过程的流水步距不等",true,{"key":20,"text":21,"correct":14},"C","专业工作队数等于施工过程数",{"key":23,"text":24,"correct":14},"D","施工段之间没有空闲时间","2020版教材P111 本题考查的是等节奏流水施工。在有节奏流水施工中，各施工过程的流水节拍都相等的流水施工，也称为固定节拍流水施工或全等节拍流水施工。其特点是：①所有施工过程在各个施工段上的流水节拍均相等；②相邻施工过程的流水步距相等，且等于流水节拍；③专业工作队数等于施工过程数，即每一个施工过程成立一个专业工作队，由该队完成相应施工过程所有施工段上的任务；④各个专业工作队在各施工段上能够连续作业，施工段之间没有空闲时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]