[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909172":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909172,587,1,"单选题","下列各项中，属于等步距异节奏流水施工的特点的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","相邻施工过程的流水步距相等，且等于流水节拍的最大公约数",true,{"key":16,"text":17,"correct":18},"B","同一施工过程在各个施工段上的流水节拍不等",false,{"key":20,"text":21,"correct":18},"C","施工过程数大于专业工作队数",{"key":23,"text":24,"correct":18},"D","施工段之间允许存在空闲时间","2020版教材P113 等步距异节奏流水施工也称为成倍节拍流水施工。特点如下：①同一施工过程在其各个施工段上的流水节拍均相等；不同施工过程的流水节拍不等，但其值为倍数关系；②相邻施工过程的流水步距相等，且等于流水节拍的最大公约数(K)；③专业工作队数大于施工过程数，即有的施工过程只成立一个专业工作队，而对于流水节拍大的施工过程，可按其倍数增加相应专业工作队数目；④各个专业工作队在施工段上能够连续作业，施工段之间没有空闲时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]