[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909169":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909169,587,1,"单选题","某工程划分为3个施工过程，4个施工段组织加快的成倍节拍流水施工，流水节拍分别为4天、6天和4天，则需要派出（ ）个专业工作队。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","6",false,{"key":20,"text":21,"correct":18},"C","4",{"key":23,"text":24,"correct":18},"D","3","2020版教材P114 本题考查的是流水施工的基本组织方式。等步距异节奏流水施工，也称成倍节拍流水施工。工期计算方法：K=2，施工队数=4\u002F2+6\u002F2+4\u002F2=7（个）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]