[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909166":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909166,587,1,"单选题","某工程划分为3个施工过程、4个施工段组织流水施工，流水节拍见下表，则该工程流水施工工期为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","22",false,{"key":16,"text":17,"correct":14},"B","23",{"key":19,"text":20,"correct":14},"C","26",{"key":22,"text":23,"correct":24},"D","27",true,"2020版教材P115 本题考查的是流水施工的基本组织方式。施工过程I：4，9，12，16；施工过程Ⅱ：3，5，8，10;施丁过程Ⅲ：4，7，12，16。KI，Ⅱ=max[4，6，7，8，-10]=8;KⅡ.Ⅲ=max[3,1,1，-2,-16]=3。T=(8+3)+16=27.",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]