[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909162":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909162,587,1,"单选题","某分部工程划分为3个施工过程、4个施工段，组织加快的成倍节拍流水施工，流水节拍分别为6、4、4天，则专业工作队数为（ ）个。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","6",{"key":22,"text":23,"correct":24},"D","7",true,"2020版教材P114 流水步距即流水节拍的最大公约数为2，各流水节拍和流水步距的比值即为专业工作队的数目。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]