[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909160":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909160,587,1,"单选题","某分部工程划分为3个施工过程、4个施工段组织流水施工，流水节拍分别为3、5、4、4天，4、4、3、4天和3、4、2、3天，则其流水施工工期为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","19",false,{"key":16,"text":17,"correct":14},"B","20",{"key":19,"text":20,"correct":14},"C","21",{"key":22,"text":23,"correct":24},"D","23",true,"2020版教材P115 累加数列错位相减取大值。采用错位相加取大差的方法，K1等于5，K2等于6，最后一道工作节拍步距累计时间12天，5+6+12等于23",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]