[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909159":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909159,587,1,"单选题","某工程分为 A、 B、C三个工艺过程，按五个施工段顺序组织施工，各工艺过程在各段持续时间均为7天， B、C工艺之间可搭接2天。实际施工中，B过程在第二段延误3天，则实际流水施工工期应为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","47",false,{"key":16,"text":17,"correct":14},"B","49",{"key":19,"text":20,"correct":14},"C","51",{"key":22,"text":23,"correct":24},"D","50",true,"2020版教材P111 本题所有施工过程在各施工段上的流水节拍都相等，因此是等节奏流水施工。T=（5+3-1）×7-2+3=50（天）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]