[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909152":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909152,587,1,"单选题","施工方案技术准备工作应包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","试验检验和调试工作计划",true,{"key":16,"text":17,"correct":18},"B","资金使用计划",false,{"key":20,"text":21,"correct":18},"C","临时用水计划",{"key":23,"text":24,"correct":18},"D","编写施工方案","施工方案施工准备。包括：技术准备、现场准备和资金准备等。 (1)技术准备。包括：施工所需技术资料的准备；图纸深化和技术交底的要求；试验检验和调试工作计划；样板制作计划以及与相关单位的技术交接计划等。 (2)现场准备。包括生产、生活临时设施的准备以及与相关单位进行现场交接的计划等。 (3)资金准备。应编制资金使用计划。 2020教材P89-99",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]