[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909144":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909144,587,1,"单选题","属于项目管理规划大纲主要内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目概况",true,{"key":16,"text":17,"correct":18},"B","组织方案",false,{"key":20,"text":21,"correct":18},"C","项目管理方式",{"key":23,"text":24,"correct":18},"D","进度计划","本题考查的是工程项目计划体系。项目管理规划大纲的主要内容包括：①项目概况；②项目管理范围；③项目管理目标；④项目管理组织；⑤项目采购与投标管理；⑥项目进度管理；⑦项目质量管理；⑧项目成本管理；⑨项目安全生产管理；⑩绿色建造与环境管理；?项目资源管理；?项目信息管理；?项目沟通与相关方管理；?项目风险管理；?项目收尾管理。2020教材P84-89",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]