[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909138":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909138,587,1,"单选题","在工程项目的计划与控制中，对工程项目从开始建设至竣工投产全过程的统一部署指的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程项目前期工作计划",false,{"key":16,"text":17,"correct":18},"B","工程项目建设总进度计划",true,{"key":20,"text":21,"correct":14},"C","工程项目年度计划",{"key":23,"text":24,"correct":14},"D","工程项目后期工作总结","2020版教材P85 本题考查的是工程项目计划体系。工程项目建设总进度计划是指对工程项目从开始建设、设计、施工准备至竣工投产(动用)全过程的统一部署。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]