[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909137":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909137,587,1,"单选题","属于项目管理实施规划主要内容的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目安全生产管理",false,{"key":16,"text":17,"correct":14},"B","项目信息管理",{"key":19,"text":20,"correct":14},"C","项目沟通与相关方管理",{"key":22,"text":23,"correct":24},"D","设计与技术措施",true,"2020版教材P88 本题考查的是工程项目计划体系。项目管理实施规划的主要内容包括：①项目概况；②总体工作安排；③组织方案；④设计与技术措施；⑤进度计划；⑥质量计划；⑦成本计划；⑧安全生产计划；⑨绿色建造与环境管理计划；⑩资源需求与采购计划；?风险管理计划；?信息管理计划；?沟通管理计划；?项目收尾计划；?现场平面布置；?技术经济指标。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]