[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909133":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909133,587,1,"单选题","（ ）是编制施工总进度计划的前提。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总体施工准备",false,{"key":16,"text":17,"correct":14},"B","主要施工方法",{"key":19,"text":20,"correct":14},"C","施工总平面布置",{"key":22,"text":23,"correct":24},"D","总体施工部署",true,"2020版教材P90 本题考查的是工程项目施工组织设计。总体施工部署是编制施工总进度计划的前提。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]