[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909122":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909122,587,1,"单选题","在项目实施中，激励、调动和发挥项目控制人员实现目标的积极性、创造性，这是工程项目目标控制的（ ）之一。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",true,{"key":16,"text":17,"correct":18},"B","技术措施",false,{"key":20,"text":21,"correct":18},"C","经济措施",{"key":23,"text":24,"correct":18},"D","合同措施","2020版教材P101 工程项目目标控制措施包括组织措施、技术措施、经济措施、合同措施。激励、调动和发挥项目控制人员实现目标的积极性、创造性，属于涉及人的措施，是组织措施。在判断某一项行为属于哪一类措施时，一般而言，涉及人的措施都是组织措施，涉及技术方面的措施为技术措施，涉及资金方面的措施为经济措施，涉及合同方面的措施为合同措施。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]