[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909120":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909120,587,1,"单选题","单位工程施工组织设计绘制施工进度计划图，首先应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","选择施工进度计划的表达形式",true,{"key":16,"text":17,"correct":18},"B","确定工作项目的施工顺序",false,{"key":20,"text":21,"correct":18},"C","确定工作项目的持续时间",{"key":23,"text":24,"correct":18},"D","计算劳动量和机械台班数","2020版教材P96 绘制施工进度计划图，首先应选择施工进度计划的表达形式。目前，常用来表达施工进度计划的方法有横道图和网络图两种形式。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]